Alberta’s timing targets for West Coast pipeline ‘best-case scenario’: CIBC analysts
CALGARY — The targeted timeline the Alberta government set out for construction to begin on a potential new West Coast oil pipeline is ambitious, with many obstacles yet to clear, analysts at CIBC World Markets wrote in a recent report.
The province aims to submit a proposal to the federal major projects office by July 1, have it designated a project of national interest by Oct. 1 and get shovels in the ground as early as Sept. 1, 2027. Oil could begin to flow around 2033 or 2034, a provincial official told a media background briefing last week.
“While we are encouraged by the continued sense of urgency, we would characterize these timelines as optimistic and reflective of a best-case scenario,” analysts Robert Catellier and Rogan Anantharajah wrote in a Monday industry update.
The Alberta government laid out those targets Friday after it and Ottawa finalized one of the last outstanding elements of the energy accord they signed late last year: an agreement on how the market price on carbon is to gradually increase to $130 a tonne by 2040.