Construction on Gateway 286 rest stop just off the Coquihalla could be completed in spring 2026
MERRITT — Kelowna-based developer Troika is eyeing a completion date in May or June 2026 for the Gateway 286 project at the intersection of Highways 5 and 97C near Merritt.
Residents passing by the former Merritt rest stop along the highways south of the city will notice some changes throughout the fall and winter. Troika expects the foundations and footings to be in before the snow falls, with vertical construction to follow.
Following a groundbreaking ceremony in 2022, Troika CEO Renee Merrifield says its crews have finished their portion of offsite works for the future rest stop and the City of Merritt is expected to wrap up its share in September.
Merrifield told CFJC Today the completion of Gateway 286 is about a year behind Troika’s timeline. She accredited the delay to ensuring the site has enough electricity for electric vehicles (EV).